Forcrete Micro-Quartz Specialty System - INSTALLATION GUIDE:
Quick note: Specialty system is designed for steam showers, countertops, staircases (steps) and any other complex functional surfaces. Unlike, the Wall System where we use acrylic base coats, this spec is fully epoxy based. It can be applied vertically or horizontally vs the Floor System where the base coats can only be put down flat.
BEFORE BEGINNING INSTALLATION
Before materials are applied, inspect the entire installation area carefully.
Check for:
Flex, movement or bounce in the substrate
Loose, unstable or damaged substrates
Large openings around plumbing fixtures
Protruding or non-countersunk screws
Uneven surfaces, ridges and high points
Cracks, voids or damaged board joints
Moisture-related concerns
Incomplete waterproofing or plumbing work
Any issues that may affect performance should be corrected before installation begins. Photograph and document existing defects and obtain written confirmation from the client where appropriate.
Electric underfloor heating must be tested and commissioned before the microcement installation begins.
All plumbing, drainage, electrical work, substrate boarding and waterproofing-related preparation should be completed before finish installation starts.
The installation area should be:
Structurally sound
Stable and free from excessive movement
Clean and dry
Protected from dust and contamination
Maintained at a suitable, consistent temperature
Properly ventilated without strong direct airflow
Free from active water leaks
Do not apply microcement over unstable, contaminated, wet or insufficiently prepared substrates. DO NOT use microcement for filling cracks, gaps, holes or leveling.
Ensure all products are from the correct batch, have been stored appropriately and are within their stated shelf life.
INSTALLATION STEPS
DAY 1:
1. Sand the substrate with 50 grit diamond pads. If applying over tile, grind the surface with 36 grip metal-bonded diamonds using an angle grinder.
2. Vacuum thoroughly.
3. Using Microfiber Roller apply Forprime DPM, broadcast 0.2-0.3 Kiln-dried Sand as you go, let cure for 3-5h depending on the temperature.
4. If using Belt and Braces System, lay Fiberglass Mesh secure in place with no gaps or overlaps using Hot Glue Gun.
5. Using Flexible Steel Trowel apply tinted MicroBase XT (aka Trowel X Base) to fully encapsulate the mesh.
*if using Fast System, broadcast sand into Forprime DPM, let it fully cure for 3-4h, sweep loose sand, sand the surfaces with a 100grit diamond pad, vacuum thoroughly and process to Step #9
*if using Standard System, skip Step #4 and proceed to Step #5.
*pro tip: while the primer is curing, use the time to tint the finish coats.
DAY 2:
6. Sweep up loose sand.
7. Sand the basecoat with 50 grit diamond pads.
8. Vacuum thoroughly.
9. Using Flexible Steel Trowel apply tinted MicroBase XT (aka Trowel X Base)
DAY 3
10. Sand Microbase XT with a 50 grit diamond pad.
11. Vacuum thoroughly.
12. Using Finishing Trowel apply tinted Micro-Quartz Coarse in Floated Technique
If the spec calls for Micro-Quartz Medium or Smooth, you still must install Micro-Quartz Coarse in Floated Technique first. MQM and MQS require the texture from the floated Coarse underneath to produce quality finish.
DAY 4:
13. Sand Micro-Quartz Coarse with 100 grit diamond pad
14. Vacuum thoroughly
If the spec calls Micro-Quartz Medium or Smooth, then using Soft Steel Trowel apply Micro-Quartz Medium or Smooth and let it cure till next day. After which sand it with 200 grit diamond pad, vacuum thoroughly and proceeding to Step #16 below.
15. Mop the dust off the surface with *dry* Microfiber Mop, remove as much residual dust as possible
16. A. If the finish is matte, then using Microfiber Roller apply 2 coats of Forshiled 2KWB 4 hours apart
17.B. If the finish is polished, then using Microfiber Roller apply 1 coat of Monoseal and let cure for 4h before using polishing pads to achieve the desired sheen level (200-400-800-1500-3000grit). Vacuum thoroughly. Using Microfiber Cloth or Microfiber Mop apply Forcrete Floor Wax.