Forcrete Micro-Quartz Floor - INSTALLATION GUIDE:
BEFORE BEGINNING INSTALLATION
Before materials are applied, inspect the entire installation area carefully.
Check for:
Flex, movement or bounce in walls and floors
Loose, unstable or damaged substrates
Large openings around plumbing fixtures
Protruding or non-countersunk screws
Uneven surfaces, ridges and high points
Cracks, voids or damaged board joints
Moisture-related concerns
Incomplete waterproofing or plumbing work
Uncommissioned electric underfloor heating
Any issues that may affect performance should be corrected before installation begins. Photograph and document existing defects and obtain written confirmation from the client where appropriate.
Electric underfloor heating must be tested and commissioned before the microcement installation begins.
All plumbing, drainage, electrical work, substrate boarding and waterproofing-related preparation should be completed before finish installation starts.
The installation area should be:
Structurally sound
Stable and free from excessive movement
Clean and dry
Protected from dust and contamination
Maintained at a suitable, consistent temperature
Properly ventilated without strong direct airflow
Free from active water leaks
Do not apply microcement over unstable, contaminated, wet or insufficiently prepared substrates. DO NOT use microcement for filling cracks, gaps, holes or leveling.
Ensure all products are from the correct batch, have been stored appropriately and are within their stated shelf life.
INSTALLATION STEPS
DAY 1:
1. Grind the substrate with 36grit metal bonded diamonds using walk-behind grinder and/or angle grinder
2. Vacuum thoroughly
3. Using Microfiber Roller apply Forprime DPM, let cure for 1.5-2.5h depending on the temperature
4. If using Belt and Braces System, lay Fiberglass Mesh secure in place with no gaps or overlaps using Hot Glue Gun
5. UsingHard Steel Trowel apply Forprime FL to fully encapsulate the mesh, broadcast 0.2-0.3 Kiln-dried Sand as you go
*if using Fast System, broadcast sand into Forprime DPM, let it fully cure for 3-4h, sweep loose sand, sand the surfaces with a 100grit diamond pad, vacuum thoroughly and process to Step-10
*if using Standard System, skip Step #4
*pro tip: while the primer is curing, usethe time to tint the finish coats
DAY 2:
6. Sweep up loose sand
7. Grind the basecoat with 36grit metal bonded diamonds
8. Follow up with a sand using 50 grit diamond pad to remove scratch marks from the prior step
9. Vacuum thoroughly
10. UsingFlexible Steel Trowel apply tinted MicroBase XT (aka Trowel X Base)
DAY 3
11. Sand Microbase XT with 50 grit diamond pad
12. Vacuum thoroughly
13. UsingFinishing Trowel apply tinted Micro-Quartz Coarse in Floated Technique
If the spec calls Micro-Quartz Medium or Smooth, you still must install Micro-Quartz Coarse in Floated Technique first. MQM and MQS require the texture from the floated Coarse underneath to produce quality finish.
DAY 4:
14. Sand Micro-Quartz Coarse with 100 grit diamond pad
15. Vacuum thoroughly
If the spec calls Micro-Quartz Medium or Smooth, then using Soft Steel Trowel apply Micro-Quartz Medium or Smooth and let it cure till next day. After which sand it with 200 grit diamond pad, vacuum thoroughly and proceeding to Step #16 below.
16. Mop the dust off the surface with *dry* Microfiber Mop, remove as much residual dust as possible
17. A. If the finish is matte, then using Microfiber Roller apply 2 coats of Forshiled 2KWB 4 hours apart
17.B. If the finish is polished, then using Microfiber Roller apply 1 coat of Monoseal and let cure for 4h before using polishing pads to achieve the desired sheen level (200-400-800-1500-3000grit). Vacuum thoroughly. Using Microfiber Cloth or Microfiber Mop apply Floor Wax